Home Offshore Wind Inter-array cable installation completed at Neart na Gaoithe offshore wind farm
March 22, 2024,
by
Adrijana Buljan
Cable burial activities at the inter-array routes within the Neart na Gaoithe offshore wind farm site have been completed, following the wrap-up of cable installation works in January.
The pre-lay grapnel run (PLGR) along the inter-array cable (IAC) routes was completed in November 2023 by the vessel Pacific Discovery.
The PGLR work started in March last year and DEME’s vessel Viking Neptun installed the first batch of IACs in May 2023.
Viking Neptun completed the inter-array cable installation on January 7 this year, with DEME’s Living Stone commencing cable burial work the day after.
Both vessels have now left the offshore wind farm site, according to the latest Notice to Mariners from the Neart na Gaoithe project team.
Posted: 10 months ago
The IAC termination and testing works, which are currently underway and are being performed by the Normand Navigator vessel, are expected to continue until May 2024.
The 450 MW Neart na Gaoithe offshore wind farm, located some 15 kilometers off the coast of Fife in Scotland, is expected to produce its first power this year.
The first of its 54 Siemens Gamesa 8 MW wind turbines was installed in July 2023.
Neart na Gaoithe is owned by the joint venture between EDF Renewables and ESB.
Posted: 3 months ago
Posted: 2 months ago
Posted: 10 days ago
Posted: 3 months ago
Posted: 16 days ago
Posted: 10 months ago
Posted: 4 months ago
Posted: 2 months ago
>>> Read full article>>>
Copyright for syndicated content belongs to the linked Source : OffshoreEnergy – https://www.offshore-energy.biz/inter-array-cable-installation-completed-at-neart-na-gaoithe-offshore-wind-farm/