Eventually, the train will travel all the way to Trim with stations at Jeanne d’Arc Boulevard, Convent Glen and Place d’Orléans.
Published Feb 26, 2024 • Last updated 3 hours ago • 1 minute read
It didn’t break any speed records, but Ottawa’s LRT is finally on its way to Orléans.
The first test run of a train along a portion of the 12.5-kilometre eastward extension of the Confederation Line occurred Sunday night, with a train travelling one stop from Blair Station to Montreal Road, said Mike Morgan, director of the LRT construction, in a memo to the mayor and members of council on Monday.
Advertisement 2
This advertisement has not loaded yet, but your article continues below.
THIS CONTENT IS RESERVED FOR SUBSCRIBERS ONLY
Subscribe now to read the latest news in your city and across Canada.
Exclusive articles from Elizabeth Payne, David Pugliese, Andrew Duffy, Bruce Deachman and others. Plus, food reviews and event listings in the weekly newsletter, Ottawa, Out of Office.Unlimited online access to Ottawa Citizen and 15 news sites with one account.Ottawa Citizen ePaper, an electronic replica of the print edition to view on any device, share and comment on.Daily puzzles, including the New York Times Crossword.Support local journalism.
SUBSCRIBE TO UNLOCK MORE ARTICLES
Subscribe now to read the latest news in your city and across Canada.
Exclusive articles from Elizabeth Payne, David Pugliese, Andrew Duffy, Bruce Deachman and others. Plus, food reviews and event listings in the weekly newsletter, Ottawa, Out of Office.Unlimited online access to Ottawa Citizen and 15 news sites with one account.Ottawa Citizen ePaper, an electronic replica of the print edition to view on any device, share and comment on.Daily puzzles, including the New York Times Crossword.Support local journalism.
REGISTER / SIGN IN TO UNLOCK MORE ARTICLES
Create an account or sign in to continue with your reading experience.
Access articles from across Canada with one account.Share your thoughts and join the conversation in the comments.Enjoy additional articles per month.Get email updates from your favourite authors.
Sign In or Create an Account
or
Article content
Article content
That’s about three weeks later than had been forecast in the last update on construction given in December.
The Alstom Citadis Spirit train crept east from Blair to Montreal Road while crews walked beside to make sure the train’s pantograph, the flexible arm that connects it to the overhead power lines, functioned properly. The testing occurred after regular Confederation Line service stopped for the night.
More testing will continue this week, Morgan said.
“Testing of the signal and train control system is expected to start this spring, after which residents will see regular, slow speed testing of trains on the line,” Morgan’s memo said.
A more detailed update on the construction schedule is expected Thursday when the city’s light-rail sub-committee meets.
Eventually, the train will travel all the way to Trim with stations at Jeanne d’Arc Boulevard, Convent Glen and Place d’Orléans.
In December, Morgan told the committee the first test runs on the eastward extension were expected at the end of January, with revenue service expected in late spring 2025.
The westward extension to Algonquin College and Moodie Drive isn’t expected to be complete until late 2026, according to the December update.
Meanwhile, the Trillium Line linking Bayview Station to Limebank with a spur to Ottawa airport is still expected to begin service in the spring, Transit General Manager Renée Amilcar told reports last week.
Recommended from Editorial
Confederation Line LRT deploys new measures for freezing rain
McGregor: Running for the bus at Tunney’s Pasture — there’s a fix for this